A good hypercare plan will set out: who is responsible for supporting the newly implemented solution, the SLAs applicable during the period, the decision rights and how you'll demonstrate that you're ready to step away. These elements need to be established prior to go-live, assigned to specific individuals and then formally handed over once complete. If these aren't done, hypercare risks simply becoming the tail of the implementation.
It's intended for IT and facilities leadership, DCOs, Facilities & Life Safety and the C-suite responsible for approving go-live. We discuss the pre-requisites, support arrangement, triage, monitoring and exit process.
PODTECH
Keep Critical Systems Steady After Go-Live
PODTECH develops bespoke digital solutions to support key infrastructure such as Data Centers, Buildings and upgrading existing solutions.
VisitTL;DR
- Following go-live, there is a period of increased focus on supporting and observing the new solution. This allows issues to be resolved, facilitates end-user uptake and transitions the environment to day-to-day operation.
- You should agree a set of pre-requisites ahead of go-live, including: defined resource(s), working hours, mechanism to manage and close issues, adequate monitoring in place and escalation route.
- Vendors may recommend a minimum duration for their solutions. However, the decision to conclude should be based on agreed exit criteria.
- Upon completion, you will want to ensure a clear handover to the appropriate support contact(s), capturing any outstanding items, relevant documentation, monitored alerts, logins and points of contact.
- Where possible, include the function(s) that will provide ongoing support in the project from an early stage.
Table of Contents
- What hypercare means after a go-live
- Before go-live: the hypercare checklist
- The hypercare support model: roles and coverage
- Triage and escalation
- Monitoring the live system
- How long hypercare lasts, and when it ends
- The handover that closes hypercare
- Our perspective
- Staffing hypercare for your next go-live
- FAQ
- Sources
What hypercare means after a go-live
Broadly, hypercare involves a period of intensified support and observation of the solution post-implementation (Salesforce definition). During this time, issues can be addressed and the environment kept running while driving user uptake and moving towards routine support.
Although its origins are typically traced to IT and large-scale implementations (e.g. ERPs), it's equally relevant to other significant interventions to an organisation. Whether implementing a new DCIM system, connecting to additional assets or removing dependency on an ageing solution, the initial period following go-live will see many of your hypotheses challenged by live activity.
As noted above, two differentiating factors between hypercare and standard support are:
- Level of support and observation. There will generally be greater breadth and depth of resourcing, and tighter SLAs.
- Finite nature. A defined period of support with identified lead(s) and a termination point. The Sitecore site identifies similar objectives for their customers.
For senior stakeholders, ensuring there is a defined endpoint to the activity is vital. Otherwise, you will incur ongoing costs with no obvious link to a P&L and an unresolved exposure.
Before go-live: the hypercare checklist
If there's one common theme behind unsuccessful hypercare activities, it's inadequate preparation. A recent blog on the SAP Community highlights several areas that should be satisfied prior to go-live, spanning resources, processes, technology and commercial considerations. As such, we'd encourage you to consider each of these in turn:
Resources
- Your support function has been made aware of, and experienced, the solution being implemented.
- Key personnel and contingencies are identified for the support team.
- Periods of support required are confirmed, e.g. 24x7 if required for your DC.
- End-users understand how to raise a query and the anticipated response.
Processes
- A process to receive, log, categorize, track and action queries is defined.
- The levels at which queries will be escalated are known and sign-off received from the customer.
- Queries will be reviewed on a day-to-day basis, with regular reporting to the wider audience. Further detail on the recommended structure and levels of resource is available in a 2025 publication from the IJMRA focused on SAP hypercare.
- The relevant signatories to the escalation chain are identified and aware of their responsibility.
Technology
- Monitoring of the live environment has been verified, covering e.g. integrations, jobs, reconciliations, KPIs and cyber. Again, this is raised in the SAP Community piece.
- Logins and authorisations for the support resource are available.
- There is a known process to revert or recover the environment in the event of a significant breakdown.
- Records exist detailing the configuration of the environment. For our clients, this would take the form of a fit-for-purpose CMDB.
Commercial
- The customer is comfortable with a definition of the environment being "fit for purpose".
- Any shortfalls are recorded and signed off by the customer.
- The end-user base feels ready to transition onto the new system. There's little point driving a programme to support a failed go-live!
See our go-live page for further considerations to take you through to this point.
Who does what, and for how long (hypercare)
A key consideration for any hypercare arrangement is the allocation of effort if a fault occurs e.g. on Day 3. Based on the Sitecore approach, we propose the following:
| Role | Function in hypercare |
|---|---|
| Technical lead | Direct and determine action(s) |
| Technical resource(s) | Undertake required activities to monitor, identify and rectify faults |
| Project Manager | Principal point of contact to end-users |
| Product Owner / Key Stakeholder | Assist with triage of activity (distinguish 'need' vs 'nice-to-have') |
| Subject matter expert(s) | Respond to specific subject-matter enquires, e.g. content, business processes |
In a DC or buildings context, there may be several SMEs to include in this list. It's important that these are identified and appointed prior to the start of the project. Typically these will be an FM, Building Management System or H&S professional. And crucially, they will likely be different to the developer(s) that have built the relevant solution.
Defining coverage and communications
You should define (and communicate) the extent of the service provided to users. This includes:
- Period - Is the service limited to normal working hours, additional periods and/or 24 x 7? This should be determined based on the criticality of the solution in production.
- Means of contacting the team - Designate a single entry point for users, and a mechanism to disseminate information on the state of play. Multiple points of contact will result in dropped enquiries.
- Frequency - Typically this will begin with a daily stand-up, reducing to a lower frequency over time as demand reduces.
It may not be feasible for your existing resources to provide this level of service, in which case you will need to engage additional staff. Whether through a dedicated team or augmented resources, we have experience of delivering both. Ideally, this should be determined pre-go-live to allow sufficient time for the new team to familiarize themselves with the environment.
Identifying and escalating faults
As above, the success of your hypercare service depends on the appropriate individual being made aware of the relevant fault. You will achieve this through a combination of: ticketing and escalations.
Ticket workflow
The Sitecore guidance suggests that tickets will be progressed through: allocated, active, awaiting further information and completed. Crucially, the user must confirm completion before the ticket can be considered closed. If the latter is omitted, expect to see re-reported faults in subsequent days.
Defining fault severities
Whilst the following is not prescriptive, it provides a useful basis from which you can develop your own scheme and set SLAs to be incorporated into the overall plan:
| Level | Nature of impact | Service expectation |
|---|---|---|
| 1 | Complete stoppage of operation(s), potential danger to life | Immediate action by a key resource; escalation to senior levels |
| 2 | Significant impact, but alternative means of operating available | Action within same day; tracked daily |
| 3 | Reduced functionality | To be addressed as per plan; discussed at the daily review |
| 4 | Non-critical improvement, or other request | Logged to the development queue, outside the scope of the service |
Having this final category is essential, otherwise the service will quickly become swamped with non-essential changes.
Escalation
Once again, the Sitecore guidance sets out a progressive escalation process from the appointed hypercare resource(s) upwards through the wider programme. Again, you should pre-agree the individuals, conditions and lead times associated with each stage. Ideally, once met, this should trigger an automatic move to the next level.
Given the potential consequences of failure in the critical environments that we operate in, greater detail is warranted on this topic, and can be found in our blog on escalating support for mission-critical IT.
Establishing baseline metrics on the running system
Of course, all of the above is futile if faults continue to go unreported by users! As noted earlier, the Sitecore guidance identifies some of the metrics that should be monitored. You will need to map these to the information generated by your solution. For example:
- Are all external data streams (BMS, PMS, NMS, etc.) feeding into the platform and doing so reliably and in full?
- Do values reported by the system correlate with other trusted inputs?
- What is the performance of the various interfaces (e.g. time taken to render dashboards, run reports, dispatch notifications)?
- Are any routines failing or generating exceptions, and if so, what remedial actions are being taken?
- Can any user metrics be gleaned (number of logins, drop-off at certain points, frequency of reported faults)?
- Have there been any concerning patterns around user permissions?
These should all be actioned periodically by a nominated individual. In addition, you will want to track a limited set of KPIs throughout the duration of the service (e.g. volume of faults received and cleared, mean time to clear L1-L2 faults, recurrent faults). As with the metrics above, you'll be looking to see a decreasing pattern towards the conclusion of the period.
Where possible, it will be advantageous to consolidate all of these across the suite of platforms that comprise the wider ecosystem. In this article, we explain why supporting a site via multiple disparate screens places staff at risk of overlooking key alerts.
Determining the length of the service
Finally, you will need to establish the
Vendor guidance will usually set out a minimum and maximum. Sitecore describes their Content Hub hypercare period as typically 2-3 weeks from the point of go live and extending if required. Further examples exist across the industry for similar durations. Clearly, larger deployments and those spanning multiple locations or in staged steps will require extended periods and should be scheduled accordingly.
As above, the timescale is indicative only. The key question is what allows you to close out the period?
Closing the period
As noted, Salesforce sets out that this will conclude when “the customer's systems are running smoothly… and the volume of service requests returns to a normal level” before transitioning back to standard support. Another reference (September 2026, ITIL-based) goes further, noting that reducing the number of incidents is insufficient in itself to allow the support function to operate autonomously and within its usual processes. These factors would reduce overall risk and increase assurance.
Based on the above, you can define a series of conditions to satisfy pre-go-live:
- There are no outstanding Sev 1-2 defects, or these have been explicitly signed off by the relevant party.
- The number of requests and recurrence has reduced to an acceptable baseline over a given consecutive period.
- A permanent support function can action and resolve defects with no input from the project.
- Appropriate monitoring and warnings are in place and managed by the support function.
- Any residual risk is assigned to an individual.
- The service is signalled as ready for BAU by the appropriate function.
Should any of these not be met, simply extend the period for that specific requirement and fix a revised closing date with clear rationale.
Transitioning from hypercare
Once the period is closed, support will continue. The itiligence blog outlines several actions that should accompany this: collate evidence to demonstrate the above points, clear or take formal sign-off on significant open items, obtain sign-off to commence BAU, validate the environment for this and identify residual risk and responsible parties.
These should be discussed at a handover session, with minutes recorded, covering:
- Outstanding defects and known errors, and respective accountability.
- Any relevant runbooks and documented learnings arising from defects observed.
- Details and credentials for any monitoring in place.
- Key points of contact and process in steady state.
- List of enhancements to be considered in due course.
Finally, a record should be kept of the individual(s) who took sign-off and the date. This provides cover for the ongoing support team (they can see what they are stepping into) and the project (their remit has now concluded).
Final thoughts
Where the consequences of failure are high, the value of a well-executed period of hypercare cannot be overstated. If your digital display fails for an hour in a high-street store, the impact may be negligible. But if your telemetry system misreports the temperature of your facility for that time, you could fail to act on a potentially dangerous situation.
For this reason, we recommend establishing the framework for your period of hypercare at the outset of the programme, and populating it with personnel who will take over in the longer term. As discussed in our previous blog on deploying teams to site and getting monitoring involved early, having the right team engaged from the earliest stage will enable them to become familiar with your solution ahead of go-live.
Having underpinned >250 programmes and provided 99.9% availability and worldwide support, we can deploy experienced, permanent resources or augment your existing function to facilitate a successful transition. We believe that if your hypercare can be designed and executed such that you meet the exit points set out above, you'll be in a good position.
Harry
Can PODTECH assist with your upcoming go-live?
Whether you are commissioning a new datacentre, construction or automating your current estate, we can work with you to develop a suitable support structure ahead of go-live. We develop bespoke software to meet the demands of critical assets and services, e.g. DCIM, telemetry, BMS and PMS, retrofit and large-scale automation. Our flexible models allow us to provide permanent teams or supplement your existing function.
You can find out more about our software development or get in touch via podtech.com.
Frequently asked questions
What key elements should my support plan cover?
You will want to ensure you have identified the key personnel (and contingency), their hours of operation, method of logging defects, classification of severity, escalation matrix, appropriate monitoring in place and how the period will conclude. All of this should be finalised prior to go-live.
How does this differ from regular support?
Your period of hypercare is a finite extension to your normal support offering. You can expect increased levels of monitoring, responsiveness and involvement from the project. Once your environment is deemed stable and the rate of incoming requests has decreased, you can revert to your standing support offering.
What period should I allow for my support function?
Again, there will be varying guidance (e.g. 2-3 weeks) depending on the complexity and scale of your activity. In any case, consider this as a starting point and look to meet the pre-agreed exit points to signal the conclusion of the period.
Who should lead this period of support?
The Technical Lead will oversee all technical activities, while the Project Manager acts as the primary point of contact with the customer(s). The Business Owner will determine what should be prioritised and sign off on go live. Following this, a Service Owner will be appointed to manage the service going forward.
Sources
- What Is Hypercare? Benefits and Best Practices (Salesforce)
- Hypercare Strategy, Accelerate Cookbook for Content Hub (Sitecore)
- Hypercare Post Go-Live Support for SAP Projects (IJMRA, March 2025)